ASL-100 in 1907, one year after having arrived in Maine
with its two siblings (ASl-101 & ASL-102), is seen here
in the Goodall Mill yard pulling a train of railroad boxcars.
Back in the fall of 1999, a small group of Seashore Trolley Museum members/volunteers discussed how we might apply for Federal and State funding to secure the major financial resources needed for the very large and very complicated complete restoration of the 1912 Portland-Lewiston Interurban No. 14, Narcissus. Off and on for decades, Museum members had worked hard to raise adequate funds to restore the Narcissus, only to have initial efforts fall far short of expectations. To keep this portion of the post somewhat brief, I'll refer to highlights of the ensuing years. In 2000, a project manager for the Narcissus was appointed and initial assessments, etc. began on the Narcissus while we sought direction on ISTEA and later TEA-21 funding. Conrad Misek, Scott Becker, and Bob Hughes provided pertinent information and prudent counsel as we considered our first steps. After having conversations and written correspondence with the Maine Department of Transportation, the decision was made to not make our initial application to the state with a request for funds for the Narcissus, but instead, chose the Museum's 1906 electric locomotive No. 100 from the Atlantic Shore Line Railway. The wooden locomotive would be a much simpler complete restoration and as a historical piece of railway equipment from the local communities in the Museum's area, we were hopeful that we could raise the matching funds locally. This blogger was appointed as the project manager.
ASL-100 arrived at the Seashore Trolley Museum in 1949 via
the Museum's "Highway Monster" tractor and trailer.
We submitted an application in 2000, but it was not approved. Reapplied during the 2002 application cycle, but it was not approved. The 2004 application was approved in 2005 with restoration work commencing late in the year 2006.
Here below is a video from September 2005 of ASL-100 leaving the carbarn to make its way to the Town House Restoration Shop.
Under its own power, ASL-100 makes its way toward the
Town House Restoration Shop in mid-September, 2005. PWM
The opposite side is seen here as ASL-100 makes its way to
the shop in mid-September, 2005. PWM
Fast forward to the ribbon-cutting ceremony that celebrated the successful completion of the complete restoration of the 1906 Atlantic Shore Line Railway electric locomotive No. 100 in September 2009.
Patricia Pierce Erikson (left) with O. R. Cummings.
O. R. Cummings was a member of the Museum for more
than 50 years. He wrote more than fifty books on New
England's electric railway systems, including the Atlantic Shore
Line Railway and the Portland-Lewiston Interurban. I couldn't
have been happier or more proud to have had O. R. be able to
have a ride on 100 that day of the ribbon-cutting.
September 25, 2009, PPE
ASL-100 looked fabulous in September 2009. PWM
Smile! PWM
The restoration of 1906 Atlantic Shore Line Railway
electric locomotive No. 100 was featured in this promo video,
"Make Your Case Video" for Seashore Trolley Museum.
Kennebunk Savings Bank Community Ballot Promo 2010.
Now, remember, those ten years (1999-2009) were all to build a great case for an application for major funding to completely restore the Narcissus. And we did submit an application for the Narcissus in 2010. In addition, we submitted an application for funding preliminary design expenses for a 22,000-square-foot transportation hall and an 8,000-square-foot education facility. The "rest" of the story will be in the next Narcissus Project Blog Post :)
Cover page/slide of 2010 enhancement
fund request made to the Maine Department
of Transportation. PWM
That next blog post will be the list of products and outcomes from the ASL-100 project as of the end of 2009. Those would be key pieces of evidence to include with the 2010 applications. Below is just one of the bullet points in that list. During the restoration of the locomotive, YouTube would only accept about four minutes of footage. So, the video clips of various aspects of the locomotive restoration are in short clips of a minute to four minutes, adding up to nearly fourteen hours. The links to all of the video clips are all here. See below. Quality is not up to today's standards. I wasn't using an HD recorder and those volunteers that contributed footage weren't using HD either. That being said, they are available for your enjoyment.
11-3-2006 The first video clip kicking off
the restoration of the 1906 electric locomotive
ASL-100. The series of ASL-100-related project
video clips is comprised of a total of 287 video
clips (nearly 14 hours). PWM
The various short video clips of the work on the 1906 electric locomotive ASL-100
2006
11-3-2006 The first is above - Donald G. Curry giving a preview
11-3-2006 #2 end pilot-square headed bolts-through truss rods11-3-2006 Through truss rods-polling pockets-coupler-train air
11-3-2006 Headlight bracket & plug-sandbox
11-3-2006 Sandbox-coupler rod-handrail-pilot-trolley pole
11-3-2006 Pilot-#2 end deck-brake rigging
11-3-2006 #1 end sills
11-3-2006 #1 end sills-train air-motors
11-3-2006 #1 end wheels-wheels-bolster-center bearing
11-3-2006 #1 end bolster-center bearing-sill
11-3-2006 Side sill-right, cross sill, side bearing,bolster-truck
11-3-2006 from underneath-radial bar-air reservoir brackets
11-3-2006 Brake materials-side sill-right-#1 end hood/resistors
11-3-2006 Resistors
11-3-2006 Resistors-headlight-roof paint
11-3-2006 Misc. materials on #1 end deck
11-3-2006 Inside cab
11-3-2006 Inside cab
11-3-2006 Brake materials-side sill-right-#1 end hood/resistors
11-3-2006 Resistors
11-3-2006 Resistors-headlight-roof paint
11-3-2006 Misc. materials on #1 end deck
11-3-2006 Inside cab
11-3-2006 Inside cab
11-3-2006 Inside cab
11-3-2006 Inside cab
11-3-2006 Outside cab-air compressor
11-14-2006 Walk-around (speeded up) before disassembly
11-14-2006 Walk-around (speeded up) grids and deck
11-17-2006 Walk-around (speeded up) #2 end
11-18-2006 Walk-around (speeded up) #2 end
11-19-2006 Removal of Air Compressor (speeded up)
11-22-2006 #1 end hood-outside cab
11-22-2006 Sills
11-22-2006 Sills
11-22-2006 Sills
11-22-2006 #1 end cab
11-22-2006 Right-side sill
11-22-2006 #2 end sills
11-22-2006 #2 end sills
11-22-2006 #2 end
11-22-2006 #2 end hood
11-22-2006 #2 end hood
11-28-2006 (Mute) interior of the cab
11-28-2006 (Mute) interior of the cab
11-29-2006 (Mute) cab being raised
11-30-2006 Mute-moving cab from #1 end
12-3-2006 Mute-walk-around cab/deck
12-22-2006 Truck work update
12-22-2006 Truck work update
12-22-2006 Brake rigging shoes, side bearings
12-22-2006 Trucks rusty condition - journals
12-22-2006 Motors condition
12-22-2006 Motors condition
12-22-2006 Motors condition
12-22-2006 Motors condition
12-22-2006 Motors and field coils
12-22-2006 Axle bearings & caps
12-22-2006 Deck and cab floor #2 end
12-22-2006 Cab area and the #2 & #1 ends
12-22-2006 Deck, sill, and hood area on #1 end
12-22-2006 #2 sill assembly process
2007
2-8-2007 Preheating spring cap for welding
2-8-2007 Bolster details
2-8-2007 Bolster details
2-8-2007 Body bolster #2 end-bolster rust
2-8-2007 Truck - wood for siding
3-2007 Magnetic drill
3-2007 Marking bearings
3-2007 Fabricating bolsters
3-2007 Making U-bolts
8-2007 Journal boxes
8-2007 Fabricating bolsters
3-2007 Magnetic drill
3-2007 Marking bearings
3-2007 Fabricating bolsters
3-2007 Making U-bolts
8-2007 Journal boxes
8-2007 Fabricating bolsters
8-23-2007 Under #1 end - sill work - new bolster
8-23-2007 Under #1 end - sill plug - new bolster
8-23-2007 New bolts - through truss rod - transom
8-23-2007 Trucks, springs, spring caps
8-23-2007 Trucks
8-23-2007 Trucks, wheels, axles
8-23-2007 sill wood, coal stove, displays
1-4-2008 Cab windows
1-4-2008 Cab windows
1-4-2008 Brake shoe head
1-4-2008 New #1 side sill
1-4-2008 New #1 side sill
1-4-2008 Turning new #1 sill into place
1-4-2008 Turning new #1 sill into place
1-4-2008 Grain of sill wood
1-4-2008 New body bolster #2
1-4-2008 #2 trucks and old motor mounts
1-4-2008 New cross sill work
2-28-2008 Brake slack adjuster, turnbuckle
2-28-2008 Pilot wood, wood for "teeth", truck work
2-28-2008 Truck work, motor mounts, brake lever
2-28-2008 Truck work - journal bearing Babbit
2-28-2008 Side-sill, new air reservoirs
2-28-2008 Wood for deck-pole pocket
2-28-2008 Cab window, sash work
2-28-2008 Sand valve-air muffler
3-18-2008 Small metal parts, muffler, turnbuckle
3-18-2008 Old air piping & old wiring
3-18-2008 Old wiring - piping
3-18-2008 Old wiring
3-18-2008 Old Wiring
3-18-2008 New air piping, sand piping-sill #7
3-18-2008 New air piping within sills-brake levers
5-15-2008 Recent deck work
5-15-2008 Recent deck work
5-15-2008 Recent deck work
5-15-2008 Wiring diagram review for locomotive
5-15-2008 Wiring placement
5-15-2008 Fitting bearings to the wheel axle
6-27-2008 Reclaimed deck boards in place
8-9-2008 Woodwork on the roof
8-9-2008 Woodwork on the roof
8-9-2008 Aspects of cab restoration
8-9-2008 Aspects of cab restoration
8-9-2008 Aspects of cab restoration
8-9-2008 Aspects of cab restoration
8-9-2008 Aspects of installing deck boards
8-9-2008 Aspects of installing deck boards
9-7&9-2008 Reclaimed red oak boards for the deck
9-13-2008 Reclaimed red oak boards for the deck
9-13&14-2008 "New" nailers
9-14-2008 # 1 End floorboards being nailed down
9-20-2008 Cab Floorboards
9-27-2008 End #1 brake valve work
9-28-2008 End #2 brake valve work
10-9-2008 Making # 2 pilot
10-16-2008 Techniques for cab woodworking
10-16-2008 Techniques for making the pilot
10-21-2008 Techniques for making the # 1 pilot
10-21-2008 Techniques for making the # 1 pilot
10-31-2008 Techniques for making a pilot
10-31-2008 Trolley pole/roof work
10-31-2008 Roof work/canvas replacement
11-3-2008 Pilot pieces preparation
11-9&11-2008 Pilot pieces preparation
11-11-2008 Truck work update
11-17-2008 Machine work on truck pieces
11-17-2008 Axle bearing installation steps
11-17-2008 Axle bearing installation steps
11-17-2008 Axle bearing installation steps
11-22-2008 Motor delivery and next steps
11-22-2008 Explanation of refurbished motors
11-22-2008 Pilot installation progress
11-15-2008 #1 end before installing pilot teeth
11-15-2008 Left sideboards of the cab
11-15-2008 Left sideboards of the cab
11-15-2008 Boards of the cab
11-16-2008 #1 end hood cover
11-21-2008 Hood work #1 end
11-22-2008 Initial work on doors
11-25-2008 Making & installing spring clips for motors
11-25-2008 Grommet replacement on motor
11-26&28-2008 Primed cab doors
11-27-2008 #1 hood doors & boards
11-28-2008 Details of motor configuration
11-28-2008 Details of motor configuration
11-28-2008 Details of motor configuration
12-2-2008 Procedures for oiling motor bearings
12-2-2008 Machining elongated holes in bearings
12-2-2008 Machining elongated holes in bearings
12-2-2008 Machining elongated holes in bearings
12-2-2008 Machining elongated holes in bearings
12-1-2008 Axle collar work
12-2-2008 Axle collar work
12-4-2008 Raising deck for motor installation
12-4-2008 Trucks being moved into position
12-4-2008 Axle collar work
12-6&7-2008 #2 end hoods
12-6-2008 Axle collar work
12-20-2008 Trucks under deck
12-20-2008 #2 end hood doors
12-19-2008 Wiring new trucks
12-30-2008 Paint removal in the cab
12-30-2008 Pilot & truck installation techniques
12-30-2008 Pilot & truck installation techniques
12-30-2008 Pilot & truck installation techniques
2009
1-3-2009 Preparing cab roof for new canvas
1-7-2009 Roof canvas being installed
1-26-2009 Moving cab to deck
1-26-2009 Moving cab to deck
2-12-2009 Nailing deck boards on the #2 end
3-19-2009 Cab roof trim work
3-20-2009 Cab roof trim work
3-20-2009 Compressor relocated under #2 hood
3-20-2009 Cab work
3-20-2009 Cab work
3-20-2009 Cab work
3-20-2009 Air governor & sill work
3-20-2009 Cab interior work
3-20-2009 Cab interior work
3-20-2009 Cab interior work
3-20-2009 Cab interior work
3-20-2009 Cab interior work
3-20-2009 Cab interior work
3-20-2009 Controller parts
4-6-2009 Cab work
4-6-2009 Grid placement
4-6-2009 Cab interior painted
4-6-2009 Air gauges
5-21-2009 Controller accelerator drum refurbishing
5-21-2009 Controller accelerator drum refurbishing
5-21-2009 Controller accelerator drum refurbishing
5-21-2009 Trolley base & controller housing work
5-21-2009 Identifying fonts for lettering
5-21-2009 Recent work on the #1 end & sandboxes
5-21-2009 Recent work on sandboxes
5-21-2009 #2 end hood roof & right side handrail
5-21-2009 Installation of various interior components in cab
5-21-2009 Installation of various interior components in cab
6-11-2009 # 1end headlight bracket & sandbox /piping
6-11-2009 Handbrake wheels & #1 hood & doors
6-11-2009 #2 end sandbox & bell
6-20-2009 #2 controller wires work
6-20-2009 #2 end controller wires work
6-28-2009 Headlight-Laconia Car Co logo-Coal stove
6-30-2009 Painting ASLRy letters on side-sill
6-30-2009 Painting ASLRy letters on side-sill
6-30-2009 Painting ASLRy letters on side-sill
6-30-2009 Headlight bracket discussion #2 end
7-1-2009 Lettering ASLRy right side sill
7-9-2009 Applying Laconia Car Company decal to left side-sill
7-9-2009 Testing horn & air leaks and & door holder
8-10-2009 "Golden Glow" Headlight Wiring
8-10-2009 Moving ASL-100 out of the restoration box
8-10-2009 Moving ASL-100 out of the restoration box
8-10-2009 Working on the "fingers" for the controllers
8-11-2009 Moving ASL-100 to the restoration shop pit
8-12-2009 Adjusting the trolley pole tension
8-12-2009 View from underneath ASL-100 - brake work
8-13-2009 Brake shoes for ASL-100
8-24-2009 Trolley pole discussion
8-24-2009 Checking continuity in grids, controllers & motors
8-24-2009 Checking continuity in grids, controllers & motors
8-24-2009 Replacing segments in #2 controller
8-26-2009 Adjusting segments & fingers in controllers
8-26-2009 Adjusting segments & fingers in controllers
8-26-2009 Adjusting segments & fingers in controllers
8-27-2009 ASL-100 operating for the first time with 600 volts applied
8-27-2009 Compressor operating & cab lights too
9-1-2009 ASL-100 powers up and moves w/600 volts 1st Time
9-1-2009 Checking clearances
9-1-2009 Checking clearances in loop #2 end
9-1-2009 Checking clearances in loop #2 end
9-1-2009 Checking clearances in look # 1 end
9-3-2009 ASL-100 on its maiden mainline inspection trip
9-3-2009 ASL-100 on its maiden mainline inspection trip
Exhibit Room Preparation
4-26-2009 "Before" view of the Exhibit Room
5-2&5-2009 Preparation of the room
5-6-2009 Priming & painting the room
5-31-2009 Progress
6-8-2009 Display work & track lighting installation
6-21-2009 Prep work for exhibit panels
7-1-2009 Initial exhibit panels installed
8-20-2009 Final exhibit panels installed
10-09-2009 John Middleton demonstrates controller display
Ribbon Cutting Ceremony
9-25-2009 NEERHS Chairman of Board, James Schantz opens the ceremony
9-25-2009 Maine State Senator Nancy Sullivan
9-25-2009 Patricia Erikson Speaks to the Education/Exhibit Component
9-25-2009 Actual Ribbon Cutting
9-25-2009 ASL-100 First Public Ride
9-25-2009 Mainline drive-by of 639, 1267, 38, and 434D
5-21-2009 Controller accelerator drum refurbishing
5-21-2009 Controller accelerator drum refurbishing
5-21-2009 Trolley base & controller housing work
5-21-2009 Identifying fonts for lettering
5-21-2009 Recent work on the #1 end & sandboxes
5-21-2009 Recent work on sandboxes
5-21-2009 #2 end hood roof & right side handrail
5-21-2009 Installation of various interior components in cab
5-21-2009 Installation of various interior components in cab
6-11-2009 # 1end headlight bracket & sandbox /piping
6-11-2009 Handbrake wheels & #1 hood & doors
6-11-2009 #2 end sandbox & bell
6-20-2009 #2 controller wires work
6-20-2009 #2 end controller wires work
6-28-2009 Headlight-Laconia Car Co logo-Coal stove
6-30-2009 Painting ASLRy letters on side-sill
6-30-2009 Painting ASLRy letters on side-sill
6-30-2009 Painting ASLRy letters on side-sill
6-30-2009 Headlight bracket discussion #2 end
7-1-2009 Lettering ASLRy right side sill
7-9-2009 Applying Laconia Car Company decal to left side-sill
7-9-2009 Testing horn & air leaks and & door holder
8-10-2009 "Golden Glow" Headlight Wiring
8-10-2009 Moving ASL-100 out of the restoration box
8-10-2009 Moving ASL-100 out of the restoration box
8-10-2009 Working on the "fingers" for the controllers
8-11-2009 Moving ASL-100 to the restoration shop pit
8-12-2009 Adjusting the trolley pole tension
8-12-2009 View from underneath ASL-100 - brake work
8-13-2009 Brake shoes for ASL-100
8-24-2009 Trolley pole discussion
8-24-2009 Checking continuity in grids, controllers & motors
8-24-2009 Checking continuity in grids, controllers & motors
8-24-2009 Replacing segments in #2 controller
8-26-2009 Adjusting segments & fingers in controllers
8-26-2009 Adjusting segments & fingers in controllers
8-26-2009 Adjusting segments & fingers in controllers
8-27-2009 ASL-100 operating for the first time with 600 volts applied
8-27-2009 Compressor operating & cab lights too
9-1-2009 ASL-100 powers up and moves w/600 volts 1st Time
9-1-2009 Checking clearances
9-1-2009 Checking clearances in loop #2 end
9-1-2009 Checking clearances in loop #2 end
9-1-2009 Checking clearances in look # 1 end
9-3-2009 ASL-100 on its maiden mainline inspection trip
9-3-2009 ASL-100 on its maiden mainline inspection trip
Exhibit Room Preparation
4-26-2009 "Before" view of the Exhibit Room
5-2&5-2009 Preparation of the room
5-6-2009 Priming & painting the room
5-31-2009 Progress
6-8-2009 Display work & track lighting installation
6-21-2009 Prep work for exhibit panels
7-1-2009 Initial exhibit panels installed
8-20-2009 Final exhibit panels installed
10-09-2009 John Middleton demonstrates controller display
Ribbon Cutting Ceremony
9-25-2009 NEERHS Chairman of Board, James Schantz opens the ceremony
9-25-2009 Maine State Senator Nancy Sullivan
9-25-2009 Patricia Erikson Speaks to the Education/Exhibit Component
9-25-2009 Actual Ribbon Cutting
9-25-2009 ASL-100 First Public Ride
9-25-2009 Mainline drive-by of 639, 1267, 38, and 434D
~~~~~~~~~~~~~~~
We continue the restoration work on the 1912, Narcissus, the only surviving high-speed, luxury interurban coach of the Portland-Lewiston Interurban.
Click Here: Narcissus Restoration-Related Posts
Being more than a century old, the stately, "Elegant Ride," Narcissus, is a gem. This shimmering precious stone of Maine transportation history is brilliantly resplendent as it emanates so many elements of history, including; time, places, people, and events, that it was coupled to, that when just a smattering of its seemingly innumerable stories are shared, the contents captivates, fascinates, then generates, interest to learn more 🙋. The majestic Narcissus is listed in the National Register of Historic Places.
Please consider joining the epic journey to complete the Narcissus Project by making a donation today!
Click Here: Donation Options
The restoration of this majestic icon of Maine's electric railway history is but one in a series of captivating stories containing an abundance of incredible coalition of narratives.
Click Here: History-Related Posts - Narcissus and Portland-Lewiston Interurban
The Narcissus is featured in the national Gold Award-winning novel, Teddy Roosevelt, Millie, and the Elegant Ride. The "Elegant Ride" is the Narcissus. Theodore Roosevelt was a passenger on the Narcissus on August 18, 1914, between Lewiston and Portland, Maine, while campaigning for the Progressive Party candidates.
Click Here: Bookstores and Businesses promoting the Narcissus Project
Independent book publisher, Phil Morse, holding
the Gold Book Award Winner plaque for
the Middle Reader category for The Eric
Hoffer Book Award. Congratulations to
award-winning Maine author,
Jean M. Flahive
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.